Will the Durham Transit Plan Prioritize Improvements for Current Riders?

Durham County, the regional transportation planning organization (DCHC MPO), and GoTriangle released three options for how to invest one billion dollars in transit tax revenues over the next twenty years. All options contained some common projects and service improvements using half the money. They differed in how to spend the remaining one-half billion dollars. One option prioritized improvements in local service and sidewalks, while including additional regional bus service. A second option prioritized investments in regional Bus Rapid Transit to Raleigh and to Chapel Hill. The third option prioritized investment in commuter rail to Raleigh. Both the Bus Rapid Transit option and the Commuter Rail option included local bus service and sidewalk improvements but there are fewer of them and they occur up to 7 to 10 years later. During the period when the Durham Transit Team was collecting public input, the Transit Equity Campaign was talking to riders about their priorities.

Erik Landfried, Bike Durham board member and manager of the Transit Equity Campaign, wrote a letter on September 9 to the staff and elected officials working on the plan to share what we heard from riders and to make recommendations for evaluating the options and developing a better final plan. The content of the letter is below:


The Transit Equity Campaign is a partnership between Bike Durham, the Coalition for Affordable Housing and Transit, Durham Committee on the Affairs of Black People, Durham Congregations in Action, and People’s Alliance. The goal of the Transit Equity Campaign is to hold the public agencies in charge of updating the Durham Transit Plan accountable to make sure the needs of current transit riders, transit workers and low-wealth BIPOC (Black, Indigenous, and People of Color) communities are the first priorities in the Transit Plan.

The Campaign appreciates the opportunity to provide comments on the Durham Transit Plan update. We are encouraged to hear that over half of the comments received on the latest round of engagement came through the Engagement Ambassadors and in-person events at Durham Station and other locations. However, engagement is only the starting point. The Campaign will be watching closely to see how the final plan addresses the needs brought up by riders, transit workers, and communities of color.

When asking people to sign onto the Transit Equity Campaign, volunteers asked a single question in addition to contact information: “What’s the most important improvement to make to the transit system?” We have summarized the responses below:

Infographic summarizing priorities from riders

Infographic summarizing priorities from riders

Many of the service and infrastructure needs should be familiar at this point - frequent, reliable service to more destinations supported by safe access to comfortable and accessible stops. These needs are addressed to varying degrees and timeframes by the three transit options that were presented to the public.

However, one-third of the responses to the question we asked were largely unrelated to service or infrastructure. Instead, they focused on driver courtesy and training, safety, cleanliness and comfort of the buses, and maintaining fare-free service. When asked how the Transit Plan would address these types of needs, the response we received from staff was:

We have communicated to GoDurham and GoTriangle the results of our stakeholder interviews and responses like this from both the Youth and Senior listening sessions.

Simply communicating these needs to the transit agencies without providing funds to address them is insufficient. If these needs supersede the need for better service or bus stops for many people in Durham, they need to be addressed with investments from the Durham Transit Plan.

The Transit Equity Campaign also has the following recommendations to better communicate the vision and projects in the final plan that is being developed:

  • Be explicit about when people can expect improvements and show these improvements at a community level. The difference in implementation timelines was one of the most important tradeoffs between each of the three transit scenarios shown to the public, but this was not clearly communicated. Showing this information system-wide is important, but individual communities need to understand what improvements will directly impact their own community and when those improvements will occur. This will require more granularity to break the improvements down by geographical area, but will lead to better engagement with riders and low-wealth communities of color.

  • Improve transparency by including ALL of the projects in the Durham Transit Plan public materials and the rationale for how those projects were chosen. There were assumed projects in each of the three transit options that were not shown to the public. This is unacceptable. These projects included service improvements such as increased frequency on crowded 15-minute bus routes and infrastructure improvements such as a new Bus Maintenance Facility. One of the core tenets of the Plan is transparency. Not including certain projects in the public materials does not meet that goal, especially ones that warrant public feedback. It is also important to communicate the rationale for why certain projects were or were not chosen. For example, the Braggtown Community Association is advocating for improved frequency on Route 9, which serves the heart of their neighborhood. No frequency improvements were shown for Route 9 in any of the three transit options and no rationale was provided for why other frequency improvements were prioritized above Route 9.

  • Include a prioritization of projects that may require additional revenue. There are clearly more transit needs in Durham than what can be funded given the current revenue assumptions in the Durham Transit Plan. It is important to present a realistic set of projects and the Campaign supports conservative revenue forecasts. However, it is also important to continue to pursue additional funding and have a prioritized list of the projects that would be next in line so that there is not a delay between receipt of these funds and implementation.

  • Measure equitable access to jobs in a more meaningful way. The Transit Equity Campaign was excited that staff followed through on our request to include measures for how job access would improve under the three transit options presented to the public. However, staff ran these measures without including any wait time and ran the analysis at 5pm on a weekday. This represents an unrealistic, best-case scenario and renders the frequency of each service moot. The results were also difficult to interpret:

The Transit Equity Campaign requests that transit staff measure access to jobs from multiple communities of color (not just Durham Housing Authority locations) using average wait time, which better reflects most riders’ experience using public transit. In addition, we recommend using the “Jane” tool to better display the access to employment improvements. Here is a before/after example using Jane:

Map of Transit Access from Oxford Manor with Existing Bus System

Transit Access from Oxford Manor with Existing Bus System

Transit Access from Oxford Manor with Existing Bus System

Map of Transit Access from Oxford Manor After Service Improvements

These maps are easier to understand and not only show the increase in job access, but also where people in select communities can get to by walking and using transit in increments of 15 minutes. In this example (which is not from any of the transit plan options), people living at Oxford Manor can see that not only has job access within a 30 minute commute - the medium blue color - increased significantly (from ~4,000 to ~19,000 jobs), but that these increases happen mostly along Roxboro Road, Horton Road, and downtown Durham.